It's 11pm on a Saturday. The weekend crew is running a short shift to catch up on an order, and the main line stops with a drive fault.
The shift lead rings the on-call fitter. No answer. The second number on the list goes to voicemail. The third is a fitter who answers, but they're fifty minutes away, they're mechanical, and the fault is in the panel. By the time anyone with the right skills is looking at it, it's Sunday morning.
Every site has an on-call rota. Far fewer have one that works at 11pm on a Saturday.
The rota on the wall isn't the rota you've got
Here's what usually goes wrong. None of it shows up until someone rings.
- The rota was swapped by text and nobody updated the sheet.
- The on-call phone is in a drawer, or flat.
- The person on call lives an hour away, or is at a wedding.
- The person on call is a fitter, and the fault is electrical. Or the other way round.
- Nobody has said what happens if the first call isn't answered in ten minutes.
You find out which of these you've got when the line stops. Or you find out on a quiet Sunday afternoon by ringing the number yourself. We'd do the second.
The right person, with the right skills
Being on call means very little if the person who answers can't fix the fault. PUWER's code of practice says "Maintenance work should only be done by people who are competent to do the work" (L22, paragraph 79). For electrical work, the Electricity at Work Regulations say nobody should do work that needs technical knowledge or experience to prevent danger unless they have it, or are suitably supervised (regulation 16).
At 11pm on a Saturday there's nobody to supervise. So a good mechanical fitter alone with a tripped servo drive is in a bad spot. They'll either fiddle with something they don't know, or stand there until Monday. Neither helps you.
Build the rota around skills as well as names. If your on-call person is mechanical, write down who they ring for electrical and controls faults, and make sure that number answers.
They'll be on their own
The weekend on-call engineer usually works alone. HSE's guide on lone working says you should "set the limits to what can and cannot be done while working alone" (INDG73). It lists working "near exposed live electricity conductors" as one of the high-risk jobs where at least one other person may need to be there.
So agree the limits before the call, not during it. No live fault-finding alone. No entry into a robot cell or a confined space alone. Someone on site knows where the engineer is and checks in. Our post on lone working on nights goes into the detail.
Rest still counts at the weekend
The fitter who's called out at 2am on Sunday is often due in at 6am on Monday. That's where rotas break people.
GOV.UK sets out the basics. Workers have the right to 11 hours* rest between working days, and to either 24 hours* without work each week or 48 hours* each fortnight (GOV.UK, rest breaks). Time on call at the workplace counts as working time. Time on call away from the workplace doesn't (GOV.UK, working hours). Some shift workers are entitled to compensatory rest instead when they can't take the normal breaks (GOV.UK, compensatory rest).
HSE goes further than the hours. Its fatigue guidance says "Compliance with the Working Time Regulations alone is insufficient to manage the risks of fatigue" (HSE, fatigue). It suggests recording working hours, overtime, shift swaps and on-call working.
In practice: if someone worked half of Sunday night, they don't do a full Monday on the tools as if nothing happened. Plan who covers that morning before you need to. Our guide to working time rules and maintenance overtime covers the limits in more depth.
What a weekend stop really costs
Here's our view. A weekend breakdown is often the most expensive one on the calendar, because nobody notices the clock.
On a weekday, a stop gets fixed in hours because people are around. At the weekend, a stop that nobody can fix sits until Monday. If the line stops at 11pm Saturday and the first engineer who can fix it walks in at 7am Monday, you've lost 32 hours of whatever that line was meant to make. Put your own cost per hour of downtime against it. Then add the order you were running the weekend shift to catch up on.
Compare that with what a reliable second line costs. Most sites don't.
Make the rota prove itself
A rota that works has a few things in common:
- A first call and a second call, with a time limit before you move on. Ten or fifteen minutes is enough.
- Skills on the sheet next to the names. Mechanical, electrical, controls, and who covers each one.
- A phone number on or near each critical machine, so the shift lead isn't hunting for it. See phone numbers on the machine.
- An outside engineer lined up as the last line, already inducted, with the drawings.
If you're building a rota from scratch, our post on on-call rotas people will actually do covers fairness and pay.
What to do on Monday
- Ring your own on-call number on a Saturday night, unannounced. Write down what happens.
- Add skills to the rota, and a named person for each type of fault.
- Agree the lone working limits for weekend callouts and brief them to everyone on the rota.
- Line up an outside engineer as your second call, before the weekend you need one.
* Daily and weekly rest periods correct as of 13 November 2026. Check GOV.UK's rest breaks guide for the latest. Paragraph numbers refer to L22, fourth edition (2014, amended 2018).