Turning breakdown data into a case for investment

"It breaks all the time" won't get you budget. How to turn a year of breakdown records into hours, pounds and a payback the finance director can say yes to.

SiteSOS team · · 5 min read

It's the budget meeting. You've asked for money for the case erector on line 2. A new drive and a proper overhaul, or a spare gearbox on the shelf at the very least.

The finance director asks how often it fails and what that costs. You say it's down all the time. Everyone on the shop floor knows it. The night shift has a name for it.

"Can you put some numbers on that and come back next quarter?"

You walk out with nothing. And on Tuesday night it stops again.

Engineers usually know which machine is hurting them. What they don't have is the numbers finance trusts. The good news is that most of those numbers are already in your breakdown records. They just need adding up.

Start with the log

Pick one machine. Don't try to make the case for the whole site at once. Pull the last twelve months of breakdowns for it and count four things:

  1. How many times it stopped
  2. Total hours the line was down, from stop to running
  3. What the repairs cost: parts, callouts, contractor hours, overtime
  4. How long it took to get the right person to the machine each time

If your log can't tell you those, that's the first job. We've written about a breakdown log that actually tells you something, and it's worth fixing before the next budget round. HSE's code of practice for PUWER makes the same point from the safety side. A detailed log "can provide information for future planning of maintenance activities" (L22, paragraph 78).

Put a price on the hours

Hours down mean nothing to finance until they're pounds. So multiply them by your cost per hour of downtime. That's lost output times margin, plus idle labour, overtime to catch up, scrap on restart and any late delivery charges. Our guide to what an hour of downtime really costs walks through each one.

Get finance to agree the cost per hour before you show them the rest. If they've signed off the rate, they can't argue with the total later.

Then add the repair costs from the log. That's what the machine cost you last year, on top of what it should have cost to run.

Don't forget the wait

Look hard at item four. On many breakdowns, the fix itself is short. The long part is the wait. The fitter on shift spent two hours on a drive fault that wasn't their trade. Nobody knew who to call. The right engineer was an hour away.

That wait is a cost, and it's often the biggest one. It also points to a cheaper fix than a new machine. Sometimes the case you should be making is for training, a second skill on nights, or an engineer you can call on for that kit. If you're making that case, see making the case to the board for another engineer.

A ten-minute breakdown debrief after each long stop is the easiest way to capture that wait as it happens.

Lay out the options

Finance want to see that you've thought about more than one answer. Give them three or four, each with a cost and what it saves:

  • do nothing and keep fixing it as it breaks
  • hold the parts that keep failing, so the wait for spares goes
  • fix the root cause: an overhaul, a redesign, or better PPM
  • replace the machine

For each one, estimate how many hours a year it would save, and price them at the agreed rate. Divide the cost of the option by the yearly saving. That's your payback in years. A short payback with a clear source for every number is hard to turn down.

Be honest with your estimates. If you think an overhaul cuts stops by half, say "we think", and say why. Point to the repeat faults in the log. Finance will trust a careful guess more than a confident one. For the bigger decision, our guide to repair or replace goes further.

Make the safety point too

A machine that keeps failing is a safety problem as well as a cost one. PUWER says equipment must be maintained in an efficient state. HSE's code of practice explains that "efficient" relates to how the condition of the kit might affect health and safety, and "is not concerned with productivity" (L22, paragraph 70).

HSE's maintenance guidance links the two. Fewer breakdowns mean "less dangerous contact with machinery", as well as "the cost benefits of better productivity and efficiency" (HSE, maintenance of work equipment). Every breakdown puts someone in the machine, often at night, often under pressure. Say that in the meeting. Count the times people had to go inside the guards last year.

Ask finance about the tax side

You don't need to be an accountant, but it helps to know the question to ask. Most plant and machinery can qualify for the annual investment allowance. That lets a business deduct the full value of a qualifying item from its profits before tax, up to £1 million* (GOV.UK, annual investment allowance). Whether it applies to your spend is a question for your finance team. But asking it shows you've thought about their side.

Keep it to one page

Put it on one sheet:

  1. The machine, and why it matters to the site
  2. Last year in numbers: stops, hours, cost per hour, total cost
  3. What's causing it, from the log and the debriefs
  4. The options, with cost, saving and payback
  5. What you're asking for, and by when

Bring the log with you, in case they ask. They might not, but you'll be glad you did.

Our view

Ask for the smallest thing that fixes the biggest number. A spare drive on the shelf and a trained engineer on nights often beat a new machine on payback. And they're easier to say yes to. If the numbers point to a new machine, you'll have the case ready. If they point somewhere cheaper, you'll get the money sooner. Either way, mean time to repair is the number to report every month after, so the board sees it move.

What to do on Monday

  1. Pick your worst machine and pull twelve months of breakdowns from the log.
  2. Agree a cost per hour of downtime with finance.
  3. Add up the time spent waiting for the right person, as well as the time spent fixing.
  4. Write the one-page case and book time with the finance director before the budget round.

* Annual investment allowance amount correct as of 27 November 2026. Check GOV.UK's annual investment allowance page for the latest. Paragraph numbers refer to L22, fourth edition (2014, amended 2018).

Cover the gap while the budget's agreed

Running a site?

SiteSOS sends vetted maintenance engineers to your site for breakdowns and shift cover. You see the hourly rates first, and you approve the timesheet from your phone when the job's done.

Get engineers on call

Are you an engineer?

Breakdowns and shift cover near you, paid by the job. Offers show where, what, how far and the least you'll earn, and turning one down never counts against you.

Join as an engineer

Read next

More on downtime and breakdowns