It's 6.15am. The palletiser's back running after four hours. The engineer's packing tools. Your fitter's writing "replaced prox on turner, OK" in the log. The shift manager has already gone to brief the day shift.
Everyone's tired. Everyone wants to go home. And in three weeks' time, on another night, the same machine will stop for the same reason. Somebody will spend two hours finding what was found tonight.
Most sites fix the breakdown and skip the lesson. The lesson takes ten minutes, and it's cheapest straight after the fix, while the people who did it are still stood at the machine.
Do it now, at the machine
Don't book a meeting for Thursday. By Thursday the engineer has gone, the fitter's on days off, and nobody can remember which sensor it was.
HSE's guide to investigating incidents puts it well. Look into things as soon as possible, because "memory is best and motivation greatest immediately after an adverse event" (HSG245). That guide is written for safety events, but the method works just as well for a breakdown. Plenty of breakdowns are near misses too. A machine that fails in a way that could have hurt someone deserves the same questions.
So keep the people who did the fix for ten more minutes. Stand at the machine, not in the office. You'll want to point at things.
Five questions
Keep it to these. Write the answers down as you go.
- What happened? A short timeline. When it stopped, when someone noticed, when it was called in, when the right person was on it, when it ran.
- What fixed it? The part, the setting, the fault found. Be exact. "Replaced prox" isn't enough. Which prox, which part number, and what was wrong with the old one?
- Why did it fail? Keep asking why until you hit something you can change.
- What slowed us down? Not the fault itself. Everything around it.
- What one thing changes, and who owns it? One action, one name, one date.
That's it. If you get past ten minutes, you're probably trying to solve it in the debrief. Write down the question and solve it later.
Keep asking why
HSG245 splits causes into three layers. The immediate cause is the obvious one. Underlying causes are the conditions behind it. The root cause is "an initiating event or failing from which all other causes or failings spring", and HSE says root causes "are generally management, planning or organisational failings" (HSG245).
On a breakdown that might look like this. The prox failed. It failed because the cable was chafing on the guard. The cable was chafing because it was rerouted after the last changeover and nobody checked it. The root cause is the changeover routine, and that's the thing to fix.
If you stop at "replaced prox", you've fixed tonight. If you get to the changeover routine, you've fixed next month as well. For a simple method that works on a shop floor, see five whys without a blame session.
What slowed us down
This is the question most debriefs miss, and it's often where the money is.
Look at the gaps in the timeline. How long between the machine stopping and someone calling it in? Between the call and the right engineer being at the machine? Between finding the fault and having the part?
On most sites, the fix itself is the short bit. The long bit is the wait. The fitter on shift tried for two hours on a fault outside their skill. Or nobody knew who to call. Or the right engineer was an hour away. Or the part was in the stores but nobody could find it.
Each of those has a cost you can put a number on, using your downtime cost per hour. Two hours waiting for the right skill on a line that costs a lot to stand is a number worth taking to your next budget meeting. If the debrief shows the same skills gap twice, put it on your skills matrix and get it covered.
No blame, or nobody talks
HSE's guidance is clear on this. Investigations "should be conducted with accident prevention in mind, not placing blame". Blaming people early is "counterproductive, because people become defensive and uncooperative" (HSG245).
On a breakdown, the operator who pressed reset three times will tell you so, if they know they won't get a telling off. That's the most useful fact you'll hear all night. Lose it and you lose the real cause.
So the shift manager sets the tone. "We're here to stop it happening again. Nobody's in trouble."
Is it reportable?
Ask it every time, even though the answer is usually no. Some equipment failures are RIDDOR dangerous occurrences even when nobody's hurt. That includes the collapse or overturning of lifting equipment, or "the failure of any load-bearing part" (HSE, dangerous occurrences). If a breakdown might be one, deal with that first and leave the scene as it is until you know. Our guide to RIDDOR dangerous occurrences sets out which failures count.
Put it in the log
The debrief notes go in the breakdown log, against the machine. Where a machine has a maintenance log, PUWER requires that "the log is kept up to date" (regulation 5). More usefully, HSE's code of practice says a detailed log can "inform maintenance personnel what actions have been taken previously" (L22, paragraph 78). That's the engineer on the next breakdown, reading what you found tonight.
A log with the debrief in it is also how you spot the repeats. We've written about a breakdown log that actually tells you something.
Our view
Ten minutes after every breakdown over an hour, no exceptions. Shorter breakdowns can wait for a weekly review. The action from each debrief goes on the job board with a name and a date, the same as a PPM task. If the same machine comes up three times, it's time for a proper root cause analysis, not another debrief.
What to do on Monday
- Print the five questions and stick them inside every panel door on your critical machines.
- Tell shift managers the debrief happens before anyone goes home, for any stop over an hour.
- Add a "what slowed us down" field to your breakdown log.
- Review last month's long breakdowns and add up the time spent waiting for the right person.
* Paragraph numbers correct as of 24 November 2026, and refer to L22, fourth edition (2014, amended 2018). Check HSE's L22 for the latest.