It's 2am and the callout engineer is at the gatehouse. The shift manager meets them, signs them in, and starts talking on the walk across the yard.
"It's the wrapper. Keeps faulting on the carriage. We've had a guard off. Mind the trucks."
By the time they reach the machine, the engineer knows the fault and not much else. Nobody's said where the isolator is, or that a second line runs on the same panel. Nobody's mentioned the hot work rule, or who has to sign off the restart. The engineer will find most of it out. Some of it they'll find out the hard way.
Gate briefs go wrong because they're made up on the spot, by someone tired, with the line stood behind them. Two minutes is plenty. But only if the two minutes were planned on a quiet afternoon.
What you owe them before they start
This part isn't optional. If someone from another firm works on your site, you have to give their employer "comprehensible information" on the risks they face and what you do about them (Management Regulations 1999, regulation 12). The person on site gets the same: instructions and information about the risks to them. When two employers share a workplace, even for one night, each has to co-operate with the other and tell them about the risks (regulation 11).
HSE's short guide to using contractors spells out the three things to cover. The risks they may face, the measures in place to deal with them, and your emergency procedures. It also says the information "should be in a form that is easy to understand" (INDG368).
There's a line in that leaflet worth pinning to the gatehouse wall: "Don't assume that contractors will be aware of all risks, even if they seem obvious to you." The forklift route your team walks round without thinking is invisible to someone on site for the first time.
For the full picture of your duties, see contractors on site: what you owe them before they start.
The card
Put the brief on one side of A4, laminated, kept at the gatehouse. One card for the site, and a short extra one for each critical machine. Read it out, hand it over, and get a signature.
The site card covers:
- Where you are, where the fire assembly point is, and the alarm sound
- Traffic: forklift routes, crossing points, the yard at shift change
- PPE for the area, and anything that needs a permit, such as hot work or work at height
- Who they report to tonight, with a mobile number
- How to stop the job if something's not right
The machine card covers:
- Make, model and where the manuals and drawings live
- Every isolation point, including air and hydraulics, and where the hasps are
- What else shares that supply or panel
- Stored energy to watch for: lifts, accumulators, receivers
- Who signs off the restart
Number five on the site card matters more than people think. HSE's guide lists "the arrangements for stopping the work" as one of the things to agree with a contractor (INDG368). A contractor who's told on arrival "if you're not happy, stop and ring me" is far more likely to say so.
If your site runs permits, our guide to permits to work covers how to keep them quick enough for a breakdown.
Send the fault before the van leaves
The fault details don't belong on the walk across the yard. They belong on the phone call, before the engineer sets off. What it was doing, the HMI alarms, what's been tried, what was changed. Send the photos. The engineer can think on the drive, and may bring the right part.
We've covered that call in machine down at 2am: the phone call that decides the next six hours. Do that well and the gate brief only has to cover safety and site rules. That's the two minutes.
Why it costs you when it's rushed
HSE's maintenance guidance warns that poor planning and unclear instructions "can lead to confusion and can cause accidents". It names maintenance during production, and contractors "who are unfamiliar with the site", as a particular problem (HSE, maintenance of work equipment). A breakdown callout is both at once.
The cost isn't only safety. A contractor who isolates the wrong panel stops your other line. One who doesn't know about the hydraulic lift loses half an hour working it out. One who doesn't know who signs off the restart waits by the machine while the shift manager is on a break. Each of those is time on your downtime clock.
The fix is cheap. A card takes an afternoon to write. The skill is in the engineer, and you can't make that up at the gate. But you can make sure a good engineer isn't slowed down by your site.
Our view
The shift manager owns the brief, not the engineer. A good contractor will ask for it, and you should never rely on that. Write the cards now, walk a new starter through them to test them, and fix anything they didn't understand.
Then use the same cards for agency and cover engineers on their first shift. The same rules apply (getting site rules right from shift one).
And when the job's done, spend ten minutes on what the brief missed. HSE's checklist asks whether you've "agreed how the job will be reviewed to learn any lessons from it" (INDG368). Our breakdown debrief shows how to keep that short.
What to do on Monday
- Write the site card, and a machine card for your three most critical machines.
- Mark every isolation point on the machine cards, air and hydraulics included.
- Put the cards at the gatehouse with a sign-in sheet for contractors to sign.
- Time a shift manager doing the brief with a new starter. If it takes more than two minutes, cut the card.