Keeping the line manager informed without slowing the fix

Every "how long?" pulls the engineer out of the machine. How to give production the updates they need on a timetable, so the fix keeps moving and nobody cuts corners.

SiteSOS team · · 4 min read

The filler's been down 40 minutes. The engineer is on their back under the infeed, torch in their teeth, chasing a sensor fault.

The line manager comes over. "How long?" The engineer slides out, wipes their hands, and explains. Ten minutes later it's the planner. Then the shift manager. Then the line manager again, because the planner asked them.

Each question costs the fix five minutes. Each answer is a guess, because the engineer doesn't know yet. And every guess that turns out wrong makes the next question come sooner.

Breakdowns run slower when nobody controls the flow of information. The people asking aren't wrong to ask. They have trailers, staff and orders to move. They just need the answer in a way that doesn't stop the work.

Why the line manager needs to know

Be fair to them. While the line's down, someone is deciding whether to move orders to another line, send the agency staff to another area, ring the haulier, or call a customer. Those decisions cost money if they're made late or on a bad estimate. We've written about how a stopped line hits your delivery promises, and the damage usually comes from late calls rather than the breakdown itself.

So keep production in the loop. Give them what they need, when they need it, without the engineer climbing out of the machine to do it.

One person carries the news

Pick one person to stand between the machine and everyone else. On most sites that's the shift lead or a second fitter. Their job is simple. They stay close enough to hear the engineer, and they do all the talking to production.

Everyone asking goes to that person, not the engineer. If the line manager comes to the machine, the shift lead meets them before they get there.

On a small site with one fitter on nights, that person might be the shift manager. Same rule. The engineer talks to one person, and that person talks to everyone else.

Updates on the clock

Agree an update time at the start, and stick to it. We'd use every 30 minutes for the first two hours, then hourly. The first update should come within 15 minutes of the engineer arriving at the machine.

Each update answers four questions, in this order:

  1. What do we know now?
  2. What are we doing next?
  3. What's our best guess, as a range?
  4. When's the next update?

"We've found the fault is on the infeed, not the filler head. Checking the sensor and its cable now. If it's the sensor, 30 to 45 minutes. If it's the cable run, longer. Next update at 4.30."

Give a range, and say what would change it. A single number becomes a promise. A range with a reason lets the line manager plan both ways.

If the engineer finds the fault early, they say so straight away. Good news doesn't wait for the clock.

Set the decision points up front

The most useful thing you can give production is a time when they should stop waiting. "If we haven't found it by 5am, plan as if this line's out until the day shift."

That gives them a clear point to act on. It also gives you a clear point to stop trying and call for help, if you haven't already. The same clock that tells production when to move orders tells you when the fix needs another pair of hands, or a different skill.

Pressure is where the shortcuts start

Here's why this matters for more than tempers. An engineer asked "how long?" every ten minutes starts to feel it. That's when people skip steps.

The common one is working live to save time. The Electricity at Work Regulations only allow live work when it's unreasonable for the kit to be dead, reasonable to work live, and suitable precautions are taken (regulation 14). A line manager waiting at the panel doesn't make it unreasonable for the panel to be dead.

The other is restarting before it's safe, with a guard still off or a lock still on. HSE's maintenance guidance points out that unclear communication "can lead to confusion and can cause accidents", and that it's a particular problem "if maintenance is during normal production work" (HSE, maintenance of work equipment). A breakdown is exactly that. If you want to see how this plays out at 3am, see production versus maintenance at 3am.

Good updates take the pressure off. When production knows the next update is at 4.30, they stop coming to the machine at 4.10.

Write it down as you go

The shift lead keeps a short log on a phone or a whiteboard: time, what was found, what was done. It makes the updates easy, because they're read off the log.

It helps at handover too. If the breakdown runs past shift change, the next team reads the log and doesn't start from scratch. The same goes for your own engineers handing over to each other (shift handovers between maintenance engineers). And the log is the starting point for the debrief afterwards.

Our view

The engineer's job during a breakdown is to fix the machine. Talking to production is somebody else's job. If you have one fitter on shift and nobody to carry the news, that's a staffing problem showing up as a communication problem. On your worst machines, it may be worth having a second engineer you can call in, so one fixes and one talks.

What to do on Monday

  1. Agree with production who carries the news during a breakdown on each shift.
  2. Put the four-question update format on a card at the shift office.
  3. Set default decision points with the planner, such as "after two hours, plan without this line".
  4. Ask your engineers how many times they were pulled out of the machine on the last big breakdown.

Get the right engineer in the machine

Running a site?

SiteSOS sends vetted maintenance engineers to your site for breakdowns and shift cover. You see the hourly rates first, and you approve the timesheet from your phone when the job's done.

Get engineers on call

Are you an engineer?

Breakdowns and shift cover near you, paid by the job. Offers show where, what, how far and the least you'll earn, and turning one down never counts against you.

Join as an engineer

Read next

More on downtime and breakdowns