It's the last week of November. Someone in the production meeting says "we'll pick that up over Christmas". That's the fourth time you've heard it this month.
The list on the workshop whiteboard has grown since September. Gearbox on the infeed. Bearings on the extract fan. The leak on the press that everyone steps round. The LEV test that's due in January. A guard that's been cable-tied since the summer.
Then the shut comes. Half the parts aren't in. Two of your fitters booked the week off back in March. The contractor you wanted is working for the site down the road. And on the 4th of January the line starts, trips, and the gearbox you meant to change is the first thing to go.
Most Christmas shuts are lost in November. The list is long, nothing is ordered, and nobody has checked who is actually working.
Start the list now, and cut it
HSE's advice is to use downtime for maintenance where you can. It avoids the clash with production when the work is done "before start-up or during shutdown periods" (HSE, maintenance of work equipment). Every site knows that. The Christmas shut is the biggest window most of us get all year.
Which is why everything ends up on the list. Be hard with it. For each job, ask:
- Does it need the line stopped, or could it be done on a normal weekend?
- If we skip it, what's the chance it stops us in January?
- Have we got the parts, or a firm date for them?
- Who is doing it, and are they here that week?
A job with no parts and no name is a wish. Wishes don't get done in a shut.
Rank what's left using your criticality ranking. Jobs on the machines that stop the whole site go first. The cable-tied guard goes on as well, because that one can't wait for a quieter year.
What usually belongs on it
Every site's list is different. These come up on most of them:
- jobs that need a long isolation: gearbox swaps, motor changes, conveyor belts, drive upgrades
- the repeat faults from your breakdown log, where a proper fix needs a day nobody has had
- statutory exams due soon, like LEV tests, LOLER exams and pressure system exams, booked for when the kit is free
- the PLC and HMI backups you've been meaning to take
- guards, interlocks and e-stops, tested while there's time to fix what fails
- panels, drive fans and filters cleaned out
- the jobs condition monitoring flagged that nobody acted on
On the exams, some dates are set in law, so check them before you book. LEV must have a thorough examination and test at least once every 14 months* (COSHH, regulation 9). If the next one falls in February, doing it in the shut with the extraction free is often the easy option.
If you're not sure what's due, your asset register should tell you. If yours can't, put fixing the register on the January list.
Parts first, then people
In our experience most shutdown jobs that slip, slip on parts. A gearbox on a long lead time ordered in December turns up in January. So order now, and get the delivery date in writing.
Then people. Here's where the real gap is. Your team wants time off over Christmas, and they've earned it. Your usual contractors are being chased by every other site with a shut on the same dates. Machine makers' engineers get booked early for the holiday weeks too.
So count the hours. Add up the labour on your cut list, then set it against who is actually on site each day. If the list needs twice the hours you've got, there are only a few ways out. Cut the list, book outside help now, or do it in a rush on the last two days. The rush is what happens by default.
Think about what skipping a job really costs. The gearbox you didn't change doesn't fail in the shut, when it would cost you nothing. It fails on a Tuesday in January, at full production rate, with trailers waiting. Every hour of that downtime is dearer than the hours you'd have paid an engineer in December.
We'd book the extra hands now, for named jobs. "Two fitters for the shut" is hard to fill. "A fitter with gearbox experience for three days, to change the infeed drive" is easy, and you get someone who has done that job before. There's more on timing in booking extra hands for a planned shutdown.
A site full of contractors needs running
The shut is when you have the most outsiders on site and the fewest of your own people to watch them. HSE warns that poor planning and unclear instructions cause accidents, more so where there are "contractors who are unfamiliar with the site" (HSE, maintenance of work equipment).
When two or more employers share a workplace, even for a few days, each one has to co-operate with the others and tell them about the risks (Management Regulations 1999, regulation 11). In practice that means:
- one person in charge of the shut each day, with a phone that gets answered
- a board showing every job, who is on it and who holds the locks
- permits for hot work and confined spaces, signed before work starts
- inductions on the first morning, before any tools come out
Our guide to what you owe contractors before they start has the detail.
Plan the restart as a job in its own right
The shut ends on a date. The restart needs as much planning as the work did.
PUWER expects kit to be inspected after "exceptional circumstances". HSE's code of practice gives major repair work as one example. Another is a change in use, for example "from an extended period of inactivity" (L22, paragraph 102). For lifting equipment, HSE lists "being out of use for long periods" as a reason for a thorough examination (HSE, thorough examinations).
Whether ten days counts is a call for your competent person. A line that's been mothballed since October is a different matter. And a machine with a new gearbox and a rebuilt guard needs proper checks before it runs.
So plan the first day back:
- bring the critical lines up a day early, if production can live with it
- put your best people on the first shift back, and keep their leave for later
- run every machine you worked on, with the people who worked on it stood there
- have cover lined up for the first week back, because that's when the breakdowns come
We cover why in the January restart.
What to do on Monday
- Write the full shutdown list, then cut it to jobs with a reason, a part and a name.
- Order every part with a lead time over two weeks, this week.
- Count the labour hours against who is actually on site, day by day.
- Book outside engineers now for named jobs and dates, before other sites do.
* LEV examination interval correct as of 25 November 2026. Check COSHH regulation 9 on legislation.gov.uk for the latest. Paragraph numbers refer to L22, fourth edition (2014, amended 2018).