It's the second week of December. Every line is running flat out. Orders are up, the warehouse is full and the trailers are booked back to back. Then two of your five engineers go down with the bug that's going round the canteen.
The three left are already on 12s. One of them has a week booked off from the 21st. The shut job list is 40 lines long, and the contractor you used last year has gone to another site.
Christmas puts two jobs on your team in the same month. Peak needs people on every shift, ready for breakdowns. The shut needs people in for planned work while everyone else is off. Most sites plan one and hope the other works out.
Map December before November ends
Get a calendar for the whole of December and the first week of January. Mark three things on it.
First, the production plan. Which lines run when, which shifts are added, when the last trailer goes out.
Second, the shut. When does it start, when do lines restart, and what work has to be done in between?
Third, your people. Holidays booked, holidays still owed, anyone on long-term sick, anyone who's already said they won't do Christmas.
Then put the bank holidays on. In England and Wales this year, Christmas Day is Friday 25 December and the Boxing Day substitute is Monday 28 December*. New Year's Day is Friday 1 January 2027* (GOV.UK, bank holidays). Check your own contracts too. Bank holidays don't have to be given as paid leave, and an employer can count them as part of statutory annual leave (GOV.UK, holiday entitlement). What your people are actually owed depends on what you've agreed.
Now look at each shift and each shut day. Where's the gap? You'll usually see two: the last fortnight of peak, and the first two days of the shut.
Peak: cover the breakdowns
During peak, the cost of a stoppage goes up. Every hour of a stopped line is an hour of orders you can't make up, and every missed trailer slot matters more. If you haven't put a number on it, what an hour of downtime really costs shows the sum.
So staff for the breakdowns you'll get. Pull last December's breakdown log. Which lines stopped, on which shifts, and for what? Make sure each shift has someone who can deal with those faults alone. A fitter on nights is no use if last year's night stoppages were all drives. Our guide to Christmas peak breakdowns covers the faults that tend to show up.
Watch the hours. Workers can't average more than 48 hours a week, normally over 17 weeks*, unless they've opted out (GOV.UK). Even when they have, HSE says the duty to manage fatigue stays with you. Accidents and injuries are higher "on night shifts, after a succession of shifts, when shifts are long" (HSE, fatigue). December is all three.
The shut: plan the people with the jobs
The shut is the one time you can get into the kit without production waiting. It's also when everyone wants to be off.
Start with the job list. Our Christmas shutdown maintenance list is a good starting point. Put hours and a trade against each job. Then add it up by day. You'll find out quickly whether your own team can do it, or whether you need outside hands.
If you need your own engineers in, tell them now. Employers can tell staff when to take leave, for example at Christmas, and can restrict leave at busy times. The notice has to be at least twice as long as the leave itself* (GOV.UK, booking time off). The contract may have its own rules. Either way, leaving it until mid-December won't work, legally or on the shop floor.
Be fair about it. Rotate who works Christmas year to year. Pay what you said you'd pay. The engineer who did last Christmas and this one will be looking for a job by Easter.
Outside cover: book it early
Here's our view. If you think you'll need outside engineers for December, book them in November.
Every site in your area has the same peak and the same shut. The good contract engineers get booked early. By the second week of December you'll be choosing from whoever is left. That's how you end up with someone who's never seen your kit, on a shift where nobody can show them round.
When you book, be specific. Name the machines and the faults. Send the shut job list for the jobs you want them on. Plan their first shift: induction, isolation points, who they report to. Booking extra hands for a planned shutdown goes through the lead times.
One thing to check if you're using agency engineers. After 12 weeks in the same job, an agency worker is entitled to the same pay as a permanent employee doing the same job* (GOV.UK). An agency engineer who started with you in late September will reach that point in December. Know who's close before you plan the rota. We cover the detail in the 12-week rule.
Don't forget the restart
The shut ends with a restart, and restarts are where lines fail. Kit that's been cold and still for a week or more gets started all at once, with everyone keen to catch up.
Keep your best people on for the restart. Don't let the whole team book the first week of January. Have someone on every line as it comes up, and plan for the faults that show up after a cold stop. Our piece on the January restart lists the usual ones.
What to do on Monday
- Put December and the first week of January on one calendar: production, the shut, holidays and bank holidays.
- Add up the shut jobs by trade and day, and compare them with who's in.
- Give notice now to anyone you need in over Christmas, and check what their contract says.
- Book any outside cover this month, with the machines and jobs named.