It's the start of nights. The operator on the flow wrapper has noticed the infeed belt is squealing. It squealed last night too. They mention it to the team leader, who says to tell maintenance. Maintenance is one fitter, and they're under the palletiser with a hydraulic leak.
By 2am the belt has thrown itself off the pulley. The wrapper's down. The fitter leaves the palletiser half done to deal with it.
Nobody did anything wrong. The operator spotted the problem 24 hours early. The system had nowhere to put what they saw.
That's what operator care fixes. The people who run the machine all shift take on the small, regular jobs and the early warnings. Your engineers keep the work that needs an engineer.
Operators already know first
Ask any fitter. When something's about to go, the operator usually knew first. The new noise. The smell. The film that's started wandering. The reject rate that's crept up since Tuesday.
HSE's guidance on lifting equipment puts it well. The user or operator "is best placed to identify faults or damage to equipment". The operator "should act as the first line of defence" (L113, paragraphs 288 and 289). That's written about forklifts and hoists, but it's true on any line.
HSE's maintenance page makes a similar point for all machinery. Along with a planned maintenance programme, it suggests "having a reporting procedure for workers who may notice problems while working on machinery" (HSE, maintenance).
So the first job is a way to report. The jobs come second.
Give them somewhere to write it
An operator who tells the team leader, who tells maintenance, who's under another machine, has told nobody.
So give the operator a direct route. A card on the machine. A defect board by the line. A button on the HMI. A simple form on the shop floor tablet that drops straight into the CMMS. Whatever it is, it has to take under a minute, and it has to reach the person who plans the work.
Then close the loop. If an operator reports a squealing belt and hears nothing back, they won't report the next one. A tick on the card and a line at the shift brief is enough. "Belt on the wrapper reported Tuesday, tensioned Wednesday, thanks."
L113 links the two. Where pre-use checks find defects, they should be reported to the maintenance team so it can "maintain a full record of identified faults" for each item (L113, paragraph 288). The same goes for the wrapper. Operator reports belong in the same history as the breakdowns. Our post on getting engineers to use the CMMS covers keeping that history usable.
What operators can take on
Start small. These are the jobs we'd hand over first:
- the start-of-shift check: guards on, e-stop tested, no leaks, no loose parts
- cleaning the machine, and looking while you clean
- checking oil and grease levels against a marked sight glass
- topping up from a labelled, colour-coded container
- checking air pressure at the regulator and draining the filter bowl
- simple tension checks on belts, against a mark or gauge
- reporting anything new: noise, heat, smell, vibration, rejects
None of this is new. HSE's short guide to work equipment says that before anyone uses a machine you should check it is complete, "with all safeguards fitted, and free from defects" (INDG291). The code of practice for PUWER gives the reason the small jobs matter. Failing to lubricate bearings or replace clogged filters "might lead to danger because of seized parts or overheating" (L22, paragraph 70).
Make each check visual. Mark the levels. Paint the gauge with a green band. Put a photo of "right" on the check card. If an operator needs to guess, the check won't get done the same way twice. Our piece on lubrication programmes that work goes deeper on the oil side.
What they shouldn't
Some jobs stay with the engineers. Anything that needs a guard off while the machine could move. Anything electrical beyond a reset they've been trained on. Adjustments that change how the machine runs. Anything where they'd need to isolate and lock off, unless they've been trained to do exactly that on that machine.
The law is clear on training. Under PUWER everyone who uses work equipment must have adequate training, including in the risks and the precautions to take (regulation 9). Supervisors and managers need it too. HSE also says maintenance work should only be done by people who are competent to do it, with enough information, instruction and training (HSE, maintenance).
So write the line down. Here's what operators do, here's what they don't, and here's who to call. If cleaning means reaching into the machine, the operator needs the same isolation training a fitter has. An e-stop is not enough.
What it buys you
Here's our view. Operator care won't cut your engineer headcount, and it shouldn't try. What it does is stop you wasting them.
Every hour a skilled fitter spends topping up oil is an hour they're not on the drive fault, the PPM or the root cause job. On a small team, that hour is often the difference between a fault caught on Tuesday and a breakdown on Thursday night. When the only fitter on shift is under the palletiser, the operator's report is the early warning you'd otherwise miss.
It also changes the 2am call. When a machine does stop, the operator can say what it was doing, what they'd noticed and what they've already checked. That cuts the first half hour off any diagnosis, whether it's your own fitter or an engineer you've brought in. It's the same idea behind the breakdown that was really an operator problem: the closer operators are to the kit, the fewer callouts are for things they could have spotted.
If you want to go further, TPM on a real shop floor picks up where this leaves off.
What to do on Monday
- Pick one line and write a start-of-shift check card with photos of "right".
- Mark the sight glasses and gauges on that line so a check needs no guessing.
- Set up one route for operator defect reports that lands in the CMMS.
- Write down the jobs operators must not do, and brief every shift on it.
Paragraph numbers refer to L22, fourth edition (2014, amended 2018), and L113, second edition (2014, amended 2018).