Restarting after a long stop: why the first hour back fails

The line ran fine before the shut. Two weeks later it won't make ten minutes. Why the first hour back goes wrong, and how to plan the restart like a job.

SiteSOS team · · 5 min read

It's 6am on the first Monday after a two-week shut. The contractors have gone, the floor's been painted and the line was running fine the day you stopped it.

By 6.20 the case erector won't pick a blank. By 6.35 the filler's hydraulic pack is low on oil and nobody knows where it went. At 6.50 a conveyor zone stops dead because a photo-eye is covered in grinding dust. Your two fitters are on three jobs, the production manager is stood at the end of the line, and the first trailer goes at nine.

None of this is bad luck. Machines change while they stand. People forget what they knew. And work done in the shut was never tested with product on the line.

What changes while it's stood

Kit that runs every day hides its faults. Stop it for a fortnight and they come out.

Seals and gaskets dry and shrink, then weep when pressure comes back. Condensation sits in air lines and goes straight into valves on the first cycle. Belts take a set where they sat round a pulley. Product left in a hopper or a pipe goes hard. Grease thickens. A slow hydraulic leak that would have shown on a daily check has had two weeks to empty the tank.

Then add what the shut did. Guards off and back on. Sensors knocked by the painters. A motor changed and wired in reverse. A setting changed on a drive by a contractor who's now in Leeds. Our post on the January restart has more on the Christmas version of this.

The law treats a long stop as a reason to inspect

PUWER says kit that deteriorates in a way that could be dangerous must be inspected at suitable intervals. It must also be inspected "each time that exceptional circumstances which are liable to jeopardise the safety of the work equipment have occurred" (regulation 6).

The code of practice lists what counts. It includes "major modifications, refurbishment or repair work" and "substantial change in the nature of use, for example from an extended period of inactivity" (L22, paragraph 102). A shut ticks both boxes on most sites.

Lifting kit is the same. HSE lists being "out of use for long periods" as an exceptional circumstance that can mean a thorough examination, along with damage, failure and major changes (HSE, thorough examinations). A hoist that sat idle all summer, or a truck that got a new mast chain in the shut, is a call to your examiner before it lifts anything.

Don't forget the water. The legionella code of practice warns against "water stagnation which may encourage the growth of biofilm". It expects your written scheme to cover "commissioning and recommissioning procedures" and "shutdown procedures" (L8). Cooling towers, process water and the showers in the locker room have all sat still. Whoever runs your water scheme needs the restart date.

Restart it the day before

Here's our view. The restart is a job in its own right. Most sites leave it to the last page of the shut plan, if it's there at all. Put it in the 12-week countdown with everything else.

Give it a shift. The day before production comes back, bring the site up with nobody waiting on output:

  1. Clear every lock. Go through the isolation register. Every lock off, and every holder confirms they're clear. If a lock is still on and its owner has gone home, follow your own procedure. Don't cut it because the line's due to start.
  2. Services first. Air, cooling, vacuum, hydraulics. Drain the air lines. Top up and check for leaks once the pressure is up.
  3. Walk every guard and interlock. Open each guard on a running machine and check it stops. Shut work often leaves one not made, or one bridged to test something.
  4. Run empty, then run with product. Dry cycle each machine. Then run a short batch while you still have time to fix what it shows.

Sensors are the usual first-hour fault. They're cheap, they get knocked, and they're easy to miss on the walk round. Our guide to sensor faults explains where to look.

Every job in the shut gets signed off

The second cause of first-hour failure is work nobody tested. A contractor changed the gearbox, put the guard back and left. It was never run under load.

Ask for a sign-off on every shut job: what was done, what was tested, what settings changed. If a drive parameter or a PLC value was touched, get the before and after. Backups taken on the last day before the shut are worth having. Taking another after it is worth more.

Ask who did it, too. L22 is clear on competence: "Maintenance work should only be done by people who are competent to do the work" (L22, paragraph 79). That applies to shut contractors as much as your own team.

Book hands for the first morning too

Most sites book extra engineers for the shut. Very few book them for the restart. Then the shut contractors leave on Friday, and Monday morning has the same two fitters it always had.

That's the wrong way round. The shut is planned work, and it can slip a day. The first morning back is when everything that changed shows up at once, with the whole site waiting. Put the extra hands there. Our guide to booking extra hands for a planned shutdown covers when to book them.

Do the sums before you decide. Every hour the line isn't running on restart morning costs the same as any other hour of downtime. Two extra engineers for one shift is usually a small number next to that.

What to do on Monday

  1. Add a restart shift to your next shut plan, with its own checklist and owner.
  2. Ask your examiner which lifting kit needs looking at after a long stop, and book it in.
  3. Make a sign-off sheet for every shut job, with tests done and settings changed.
  4. Book cover for the first morning back as well as the shut itself.

Paragraph numbers refer to L22, fourth edition (2014, amended 2018). L8 is the fourth edition (2013).

Have extra hands booked for the morning you restart

Running a site?

SiteSOS sends vetted maintenance engineers to your site for breakdowns and shift cover. You see the hourly rates first, and you approve the timesheet from your phone when the job's done.

Get engineers on call

Are you an engineer?

Breakdowns and shift cover near you, paid by the job. Offers show where, what, how far and the least you'll earn, and turning one down never counts against you.

Join as an engineer

Read next

More on downtime and breakdowns