It's 9pm, the Monday after Black Friday. The main take-away conveyor from pick to pack has stopped. A drive has tripped, or a zone has died, and nobody's sure which.
The pickers keep picking. Totes stack up at the end of every aisle. Within ten minutes a supervisor has twenty temps carrying totes by hand to the pack benches. Your engineer is under the conveyor with a torch, and the ops manager wants to know if you'll make the last trailer.
A conveyor stop in peak is a breakdown with a crowd round it. The fault is often simple. The risk is everything people do while they wait.
Find out where it actually stopped
On a long system, the place where totes are stacking up is rarely where the fault is. Walk it. Look at every drive, every zone and every merge.
The usual suspects, in our experience:
- a drive tripped on overload because something jammed upstream
- a photo-eye knocked, dirty or out of line at a merge
- a motor driven roller or zone card dead on a powered roller section
- a belt off track, or a splice starting to go
- an e-stop or pull wire tripped and not reset, often by someone who didn't know they'd done it
Read the fault before you reset anything. A drive that trips again five minutes after a reset is telling you about a jam, a bearing or a belt. Our guides to roller conveyor faults and the conveyor that won't track go through the checks in order.
Don't clear it running
In peak, everyone wants the jam out now. That's when people reach in.
HSE's warehousing guide lists the main conveyor hazards. They include drawing-in hazards "between the belt and head and tail pulleys", at transfer points, and between powered and non-powered rollers (HSG76, paragraph 477). Those are exactly the spots where totes jam.
The PUWER code of practice says that for jobs outside the normal sequence, "such as clearing blockages, setting or cleaning", proper controls should be provided (L22, paragraph 168). And an e-stop is not isolation. Interlocked guards and emergency stops "are not suitable as a means of isolation" (L22, paragraph 195). If a hand is going near a pulley or a nip point, that section is locked off first. Our guide to lock off, tag out, prove dead covers how.
Restarting with people all over it
Once it's fixed, the restart is its own risk. During the stop, people have been leaning on the conveyor, stepping over it and stacking totes on it.
HSG76 says e-stops on conveyors should be designed so "manual resetting by an authorised person is necessary". It also says you need a safe system of work for long or complex systems. That covers when the system is started at the beginning of a shift "or after an emergency stop has been used" (HSG76, paragraph 478).
So one person resets and restarts. Before they do, someone walks the length and clears people off it. Use the start-up warning if you have one. Then run it empty for a minute before the totes go back on.
Watch for guards, too. HSG76 gives the example of an engineer servicing a conveyor who "could remove a guard for access and not replace it" (HSG76, paragraph 55). At 9pm in peak, with the ops manager waiting, it's the easiest thing to skip.
The workaround is a risk of its own
Carrying totes by hand keeps orders moving. It also turns a picking job into a manual handling job nobody assessed.
The Manual Handling Operations Regulations say you should, so far as is reasonably practicable, avoid manual handling that risks injury. Where you can't, you have to assess it and reduce the risk (regulation 4). HSG76 points the same way: use trolleys, pallet trucks, conveyors and other aids to avoid moving loads by hand (HSG76).
So plan the workaround before peak, not on the night. Where do the totes go? On what? Who decides when to stop picking? And remember who's doing it. HSG76 says to take into account agency workers' "lack of experience and familiarity with the work" (HSG76, paragraph 50). In peak, that's most of your floor.
What a peak stop costs
Here's our view. In peak, the main conveyor is the site. When it stops, pick rate drops to whatever people can carry, pack benches go quiet, and trailers wait or leave short.
Do your own sums. Take the orders per hour that line moves, the value of a missed trailer slot, and the overtime to catch up tomorrow. Then ask how long you can afford to wait for an engineer to drive in. Most sites find the answer is not very long. See late trailers and missed slots for how the costs stack up.
That's why peak cover gets booked in September, not the week it's needed. An extra engineer on nights through peak, who already knows your conveyor, is worth more than the fastest callout from someone who's never seen it. Our guide to peak season engineering cover covers when to book.
What to do on Monday
- Walk your main conveyor and list the spares a peak breakdown would need. Drive, belt, rollers, zone cards, photo-eyes. Check they're on the shelf.
- Write a one-page restart routine: who resets, who walks the line, how long it runs empty.
- Plan the manual workaround now, with the trolleys and the routes, and brief the shift leads.
- Book your peak engineering cover before the volume arrives.
Paragraph numbers refer to HSG76, second edition (2007), and L22, fourth edition (2014, amended 2018).