Most falls in maintenance come from the quick job: a photo-eye, a roof fan, a high conveyor. What the Work at Height Regulations ask, and what to change.

SiteSOS team · · 6 min read

It's 3am. A photo-eye on the high-level conveyor has been knocked out of line, and totes are backing up into the pick zone. It's four metres up. The scissor lift is on charge at the far end of the building, and the only person who's driven it is on days.

There's a stepladder by the maintenance cage. Your night fitter looks at it, looks at the conveyor, and does the maths. Two minutes up there with a hex driver. What could go wrong?

Most falls on maintenance work don't come from big planned jobs. They come from the quick job, done with the wrong kit, by someone on their own because nobody else is on.

Height means any height

The Work at Height Regulations 2005 don't start at two metres. Work at height means work in any place where a person could fall "a distance liable to cause personal injury" if nothing was done to stop it. That place can be at or below ground level (regulation 2). So the inspection pit under a conveyor counts. So does the top of a machine guard, a mezzanine with a handrail section unbolted, and the second tread of a stepladder.

HSE's FAQs put it simply. You're working at height if you could fall from an edge, through an opening or fragile surface, or from ground level into a hole. A trip on the level doesn't count, and nor does walking up a permanent staircase (HSE, work at height FAQs).

The duties sit with employers and with anyone who controls work at height. HSE names facilities managers and building owners who bring others in to do it.

Avoid, prevent, then minimise

Regulation 6 sets the order. First, don't work at height if the job can be done safely another way. Where you can't avoid it, use a place of work that's already safe, or kit that stops a fall happening. Only when that doesn't remove the risk do you move on to kit that cuts the distance and the consequences of a fall (regulation 6).

HSE's brief guide calls these steps avoid, prevent and minimise. Its first piece of advice is to do as much work as possible from the ground, with ideas like extendable tools and lowering a lighting mast instead of climbing it (INDG401).

On a factory floor that means real questions. Can the photo-eye bracket move so it's reachable from a walkway? Can the high-bay lights go on a lowering winch? Every job you design out is a fall that can't happen at 3am.

When you can't avoid the height, collective protection comes before personal protection (regulation 7). A guard rail or a scissor lift protects whoever is up there without them doing anything. A harness only works if the person puts it on right and clips onto a good anchor. So the scissor lift beats the harness, and the harness beats nothing.

The stepladder isn't banned

Plenty of people think ladders are banned. HSE calls that a misconception (INDG401). A ladder can be the right kit for low-risk, short jobs. As a guide, if a task means staying up a leaning ladder or stepladder for more than 30 minutes* at a time, HSE suggests you look at other equipment (HSE FAQs).

But a short job doesn't make it a ladder job. HSE says short duration "is not the deciding factor". You look at the risk first. Picture a stepladder next to a running conveyor, a fitter reaching sideways to a sensor, and a floor wet from a leak. However quick that job is, the risk is high.

Here's our view. If your fitters keep reaching for a ladder to get to the same spot, that spot needs a platform. Price it up.

Roofs and roof lights

Factory and warehouse roofs are full of kit: extract fans, air handlers, gutters, roof lights. HSE says falls through fragile roofs and roof lights are one of the most common causes of workplace death and serious injury. They happen on factory and warehouse roofs during repair and cleaning work. The same leaflet lists what's likely to be fragile, from roof lights and liner panels to corroded metal sheets (INDG401).

Treat every roof as fragile until someone competent tells you otherwise. A tripped roof fan can wait for daylight and the right kit.

Plan the rescue as well as the job

Regulation 4 says work at height must be properly planned, supervised and done as safely as is reasonably practicable. The planning has to cover emergencies and rescue. The work also has to wait if the weather puts people at risk, which matters for roof jobs in November (regulation 4).

Rescue is the bit that gets missed. If your fitter is hanging in a harness off a high beam, who gets them down, and with what? HSE's guide tells you not to rely entirely on the emergency services for rescue in your plan. On nights with one fitter on site, there may be nobody to raise the alarm at all. If that's your set-up, read our piece on lone working for your night engineer before the next roof job.

Willing isn't the same as competent

Regulation 5 says nobody takes part in work at height, including planning and supervising it, unless they're competent, or in training under someone who is (regulation 5). For a short ladder job that might be no more than being shown how to use the ladder safely. Harder jobs need more. HSE points to industry training and certification schemes as one way to show it. For MEWPs and towers, most sites look for IPAF or PASMA.

This is where breakdowns get dangerous. The person who can drive the scissor lift is on days. The person on nights is willing, but has never used one. So the job gets done off a ladder, off the top of a guard, or off the forks of a truck. Each of those is a fall waiting to happen.

The other choice is to leave the line down until days come in. On a busy night in a warehouse in peak, that's hours of lost picks. Neither option is good. The fix is having someone with the right training on every shift, or lined up to come in.

Check the kit before it goes up

Kit whose safety depends on how it's put up must be inspected once it's in place. Kit exposed to conditions that cause it to deteriorate needs inspecting at suitable intervals, and after anything that could affect its safety. The results have to be recorded. Kit that comes from another business, like a hired tower, must arrive with evidence of its last inspection. Working platforms used for construction work, where someone could fall 2 metres* or more, need an inspection within the previous 7 days* (regulation 12).

HSE lists ladders among the kit you keep inspection records for (INDG401). A scissor lift is lifting equipment too, so it also needs its LOLER thorough examination. And the task itself needs a risk assessment people will actually read, not one filed in a drawer.

What to do on Monday

  1. Walk the site and list every place your fitters climb to on a breakdown: sensors, valves, lights, roof fans.
  2. For each one, ask if it could be done from the ground or a fixed platform. Price the worst three.
  3. Check who can use the scissor lift or tower on every shift, and fill the gaps.
  4. Write a rescue plan for any harness work, and make sure the night shift can follow it.

* The 30-minute ladder guide and the 2-metre and 7-day inspection rules for construction work platforms correct as of 14 November 2026. Check the Work at Height Regulations on legislation.gov.uk and HSE's work at height pages for the latest.

Get the right engineer up there, with the right kit

Running a site?

SiteSOS sends vetted maintenance engineers to your site for breakdowns and shift cover. You see the hourly rates first, and you approve the timesheet from your phone when the job's done.

Get engineers on call

Are you an engineer?

Breakdowns and shift cover near you, paid by the job. Offers show where, what, how far and the least you'll earn, and turning one down never counts against you.

Join as an engineer

Read next

More on legal duties on site