How many engineers does your site need? A way to work it out

Headcount gets set by last year's budget, not by the work. A simple way to count the hours your site really needs, shift by shift.

SiteSOS team · · 5 min read

It's Tuesday, 3pm. The case erector on line 2 has stopped again. Your day fitter is halfway through a gearbox swap on the mixer. The electrician is on a course. The shift manager wants to know who's coming.

Nobody is coming. You've got four engineers for a site that runs 24 hours a day, five days a week, and two of them are on days.

Ask most managers how many engineers they need and they'll tell you how many they've got, plus one. The number came from the last budget, and the budget came from the year before. Nobody worked it out from the work.

Start with seats, not people

The first question is how many engineers you need on site at once. Call each one a seat.

Walk the shift pattern. On days you might need a fitter and an electrician. On nights, maybe one multi-skilled engineer who can do both. At weekends, maybe nobody, or someone on call. Write it down as a grid: shifts across the top, seats down the side.

Then count the hours. A seat covered 24 hours a day, seven days a week, is 168 hours. A seat on days only, five days a week, at eight hours, is 40.

That's your demand. Now you need to work out how much one engineer can supply.

One person doesn't fill one seat

This is where most headcount plans fall over.

Take an engineer on a 40-hour week. They're entitled to 5.6 weeks of paid holiday a year* (GOV.UK). That leaves about 46 working weeks. Take off training days. Take off sickness. Take off the odd day lost to a hospital appointment or a kid's school play. Use your own records for those. Your HR system will have last year's figures.

Say you end up with 44 weeks. That's 1,760 hours a year from one person.

A 24/7 seat needs 168 hours a week, every week of the year. That's 8,736 hours. Divide one by the other and you need five people to keep one seat filled. Not four. Five, before anyone leaves.

Run the same sum for your own pattern. A 24/5 site, a 12-hour continental, a double day shift. The numbers change. The point doesn't. If you staff one person per seat per shift, you've staffed for a year with no holidays, no courses and no flu.

Overtime fills the gap until it doesn't

Most sites fill the shortfall with overtime. It works for a while. The same three people pick up the extra shifts, the rota holds, and the plan looks fine on paper.

There are limits. Workers can't work more than 48 hours a week on average, normally averaged over 17 weeks*, unless they've opted out (GOV.UK). They're also entitled to 11 hours' rest between working days* (GOV.UK). An engineer who finishes a double at 10pm can't be back in for 6am.

The opt-out doesn't make the problem go away. HSE says the duty to manage fatigue sits with the employer, "irrespective of any individual's willingness to work extra hours". It adds that keeping to the Working Time Regulations alone "is insufficient to manage the risks of fatigue" (HSE, fatigue). A tired fitter on their sixth night isolating a palletiser is the risk you're carrying. We've covered where that line sits in overtime as cover.

Then add the work

Seats tell you how many people you need to be on site. They don't tell you whether those people can get the work done.

So check it from the other side. Pull two numbers.

The first is planned work. Add up the hours on your PPM schedule for a year. If your schedule doesn't have hours against each task, that's the first job. Guess them with the fitters, then correct them as the jobs get done.

The second is breakdown work. Pull the hours from your breakdown log for the last 12 months. If your log can't tell you that, it needs fixing before it can tell you anything. There's a guide to a breakdown log that actually tells you something.

Add the two. Then add time for the jobs that never make it into either: projects, line changes, the new machine going in next spring, the audit prep. Compare the total with the hours your team can supply.

If the work is bigger than the hours, you'll see it in your PPM. Tasks slip, then get skipped, then breakdowns go up. PUWER expects equipment to be "maintained in an efficient state, in efficient working order and in good repair" (regulation 5). A PPM that never gets done because there's nobody to do it is a gap you'll have to explain.

The right mix matters as much as the number

Five engineers isn't the answer if all five are mechanical fitters and your worst downtime is drives and PLCs.

Go back to your breakdown log. Sort the last year's stoppages by trade. Mechanical, electrical, controls, pneumatics. Then look at who's on each shift. If the night shift fails on controls faults and your night engineer is a fitter, you don't have a headcount problem. You have a skills problem on one shift. The two need different fixes. A skills matrix will show you where.

Put a price on the gap

Here's our view. The sum above will usually tell you that you're short. The board will usually tell you there's no budget. You need a third number to settle it.

Work out what an hour of downtime costs on your worst line. Lost output, idle operators, scrap on restart, missed trailers. Then look at how many hours last year were down to waiting. Waiting for the fitter to finish another job. Waiting for the electrician to come in. Waiting for someone who knew the machine. What an hour of downtime really costs walks through the sum.

Multiply the two. Put that next to the cost of one more engineer. If the waiting costs more, you have your case for the board. If it doesn't, you've learned something too. Maybe what you need is cover for the gaps rather than a new post: someone for holidays, the shut, or nights when the regular engineer is off.

What to do on Monday

  1. Draw your seat grid. Shifts across the top, the trades you need on site down the side.
  2. Work out the hours one engineer really gives you in a year, using last year's holiday, training and sickness figures.
  3. Pull last year's breakdown hours by trade and shift, and add your PPM hours.
  4. Put a cost on the hours lost waiting for an engineer, and take it to the next budget meeting.

* Holiday entitlement, the 48-hour average and 17-week reference period, and the 11-hour daily rest figure correct as of 10 November 2026. Check GOV.UK on working hours and GOV.UK on holiday entitlement for the latest.

Fill the gap while the numbers catch up

Running a site?

SiteSOS sends vetted maintenance engineers to your site for breakdowns and shift cover. You see the hourly rates first, and you approve the timesheet from your phone when the job's done.

Get engineers on call

Are you an engineer?

Breakdowns and shift cover near you, paid by the job. Offers show where, what, how far and the least you'll earn, and turning one down never counts against you.

Join as an engineer

Read next

More on engineers and cover