It's 3.40am. The lights flicker, the compressors wind down and the whole site goes quiet. Thirty seconds later the power's back.
Half the line sits there with a fault on every HMI. The case packer has started itself. The wrapper is halfway through a cycle with a pallet on the turntable. Your one fitter on nights is walking the floor trying to work out where to begin, and the shift manager is already asking when you'll be running.
A power cut stops every machine at the same moment. Losing the power rarely hurts anyone. Getting it back, with nobody in charge of the order, can.
A dip can be worse than a cut
A full cut is the easy one. Everything stops and everyone knows it.
A dip is harder. A second or two of low voltage can drop some contactors and not others. Drives trip on undervoltage. A PLC rides through on its own supply while the outputs it controls went dead. You end up with half the site in a state nobody designed for, and the HMIs don't always tell you which half.
Then there's the loss of one phase. Motors can keep turning on two, running hot and noisy, until the overloads go. If the lights stayed on but three conveyors stopped, think phase before you think motor.
What the machine should do when the power goes
PUWER expects control systems to handle this. A control system isn't safe unless it makes sure, so far as is reasonably practicable, that "the loss of supply of any source of energy used by the work equipment cannot result in additional or increased risk" (regulation 18). The code of practice says failure of a control system or its power supply "should lead to a 'fail-safe' condition", and that it "should always be possible to recover to a safe condition" (L22, paragraph 193).
Restarting is covered too. Regulation 14 applies to starting kit "including re-starting after a stoppage for any reason". That has to need a deliberate action on a control (regulation 14). And you have to take steps so that reconnecting an energy source doesn't put the people using the kit at risk (regulation 19).
Newer machines are built to the same rule. The machinery supply regulations say an interruption, the return of the supply or a fluctuation "must not lead to dangerous situations". The machine "must not start unexpectedly" (Supply of Machinery (Safety) Regulations 2008, Schedule 2, 1.2.6).
So in theory, every machine on site sits still after a cut until someone presses start. In practice it doesn't always. Older kit, a panel someone modified, a drive set to auto-restart, a conveyor zone that wakes up when its sensor clears. Find out which of yours do it on a quiet afternoon, before the next cut finds them for you.
Some kit is only safe while it has power
Here's the trap. L22 points out that sometimes the power supply is "helping to keep the equipment or parts of it safe" (L22, paragraph 198). Lose it and you lose that protection.
Think vacuum grippers holding a case. Air-held clamps. A hydraulic axis held up on a valve. The machinery regulations say that when the supply fails, no moving part "or piece held by the machinery must fall or be ejected". That's the design aim. On a 20-year-old robot cell, check it before you trust it.
Stored energy is the other half. The air receiver is still full after the compressor stops. A lift table can creep down as pressure bleeds off. Before anyone reaches in to clear a half-finished cycle, isolate it properly and deal with what's left in the machine. Our guide to lock off, tag out, prove dead goes through it.
Bring the site back in order
Here's our view. One person runs the restart, and everyone else waits for them. The worst restarts we see are the ones where six people press six reset buttons at once.
A restart order that works on most sites:
- Everything to stop. Local selectors off, start buttons left alone, until the supply has settled.
- Check the supply. Was it the grid or your own switchroom? Look at the incomer and any tripped breakers. Don't restart on a supply that's still dipping.
- Services first: compressed air, cooling, vacuum, hydraulic power packs. Give the air time to build. If the compressors won't come back, read compressed air down before anything else.
- Then the controls. Is every PLC in run, with its program intact? A flat backup battery shows up after a cut. See when the PLC loses its program.
- Then the lines, one at a time. Walk each machine first. Look for product mid-cycle, a half-lifted load, a robot stopped mid-move. People clear, then start.
Photograph each HMI and fault list before anyone resets it. Drives in particular will tell you whether they saw undervoltage, overvoltage or something else. Our post on inverter trips explains what each one means.
And don't start everything together. Twenty motors starting at once can pull enough current to trip the main incomer again. Stagger them.
When something won't come back
A breaker that trips again the moment you reset it is telling you something. Don't keep resetting it. Find out why.
A cut can also be where damage shows up. Where an electrical short circuit or overload makes equipment fail and causes a fire or explosion, it can be a RIDDOR dangerous occurrence. It's reportable if the kit is out of action for over 24 hours*, and the event could have killed someone (HSE, dangerous occurrences). If you smell burning in the switchroom, leave the scene as it is and find out.
The cost is in the hour after
The cut itself might last thirty seconds. The restart can take the shift.
Do the sums for your own site. Say you have twelve machines with faults, and your fitter takes twenty minutes on each. That's four hours with the site waiting on one person. Put your cost per hour of downtime against that, and a second engineer on the phone starts to look cheap. Our guide to what an hour of downtime really costs shows how to get the number.
What to do on Monday
- List every machine that restarts by itself after a power loss. Fix it, or label it and brief every shift.
- Write a one-page restart order for your site: services, controls, then lines. Pin it in the switchroom.
- Check the backup batteries and program backups on your critical PLCs.
- Agree who your night fitter calls when there are twelve faulted machines and only one of them.
* RIDDOR's 24-hour test for electrical incidents correct as of 9 November 2026. Check HSE's dangerous occurrences page for the latest. Paragraph numbers refer to L22, fourth edition (2014, amended 2018).