It's the monthly ops meeting. Slide 14 is maintenance. PPM compliance 96%. Green. Uptime 91%. Amber, but up on last month. Everyone nods and moves on to the warehouse.
Meanwhile the shrink wrapper has stopped 23 times this month. Each stop was short, so none made the downtime log. The night fitter has been on it most shifts. Nobody in the room knows, because nothing on slide 14 counts it.
Most maintenance KPIs measure what's easy to count. The numbers that tell you where your engineers' hours go are harder to collect, so they don't get collected.
Pick fewer numbers
HSE's guide to managing for health and safety makes a point that fits any dashboard. "Selecting the right measures to use is the critical step." Using the wrong ones "will cause a lot of unnecessary and unproductive effort" (HSG65).
We've all seen it. A team that spends Friday afternoon closing PPM jobs so the percentage looks right. A downtime figure that only counts stops over ten minutes. A board that sees green and stops asking.
Here's our view. Five numbers, looked at every week, beat twenty looked at once a month. These are the five we'd start with.
1. Downtime on your worst machines, in hours and money
Not site uptime. Hours lost on the five machines that hurt most when they stop, and what those hours cost. If you haven't ranked your kit yet, start with criticality ranking. Then put a price on it with what an hour of downtime really costs you.
Count the short stops too. Twenty-three five-minute stops is nearly two hours, plus every restart. A log that only counts long stops hides your worst machine.
2. Time to repair, split into waiting and fixing
Mean time to repair is the number your board should be asking about. But one figure hides two problems.
Split it. How long from the stop to someone competent on the job? And how long from there to running? The second is about skill, spares and fault-finding. The first is about people.
On a lot of sites the waiting is the bigger half. The fitter on shift is mechanical and the fault is in the drive. The controls engineer is on days. The callout list has one name on it and they're not answering. Your MTTR looks like a repair problem, but it's really a staffing gap. That changes what you spend money on.
3. Repeat failures
How many breakdowns this month were on a machine and part that failed in the last 90 days? Pick your own window, but stick to it.
This is the number that shows whether your team is fixing faults or just resetting them. A high count tells you to look at root cause methods, not more overtime.
4. Planned work as a share of all hours
Of the hours your engineers booked, how many were planned? Track the trend, not a target someone read about. If it falls for three months, breakdowns are eating your PPM. We go into the balance in planned versus breakdown maintenance.
5. PPM tasks that found something
PPM compliance tells you the job was closed. It doesn't tell you the job was worth doing.
So count how many PPM tasks found a defect and raised a follow-up job. A task that never finds anything in two years is a candidate to stretch or drop. A breakdown on a machine that passed its PPM last week is a task that's checking the wrong thing.
Leading and lagging
HSG65 asks you to look for leading indicators as well as lagging ones. It also calls them active and reactive. Active methods are preventive, like routine plant inspections and planned function checks on important plant. Reactive methods look at what's already gone wrong (HSG65).
Downtime and repeat failures are lagging. They tell you what happened. Planned share and PPM findings are leading. They tell you what's coming. You need both, or you'll only learn about a problem once the line's stood.
The faults your dashboard can't see
One more thing from HSE, and it matters. The PUWER code of practice points out that a fault which affects production "is normally apparent within a short time". A fault in a safety-critical system "could remain undetected" unless safety checks are part of the maintenance (L22, paragraph 71).
Every production KPI on slide 14 would stay green with a light curtain that's stopped working. So keep one line on the dashboard for safety function tests: interlocks, e-stops, light curtains. Done or not done, and what failed. The same code says "efficient" in PUWER is about safety. It is not concerned with productivity (L22, paragraph 70).
Make it weekly, and make someone act
HSG65 says monitoring needs to be timely. It also says the results have most impact when they reach the people who decide (HSG65). A monthly slide that nobody acts on is just a report.
So put the five numbers on one page every Monday. For each one that's moved the wrong way, name one action and one owner. If the waiting time is climbing, that's a conversation about cover and callout lists. If repeat failures are climbing, that's a root cause session on the worst machine.
And keep the fitters in the loop. If they see their breakdown log turning into decisions, the data gets better. If they only see targets, it gets gamed.
What to do on Monday
- List your five worst machines and pull last month's downtime for each, short stops included.
- Split your last ten breakdowns into waiting time and fixing time.
- Count the PPM tasks that found nothing in the last year.
- Add a safety function test line to the maintenance dashboard.
Paragraph numbers refer to L22, fourth edition (2014, amended 2018).