UKCA and CE marking on new machinery

The new machine has a plate, a mark and a declaration in the envelope. What those prove, what they don't, and the checks that are still yours to make.

SiteSOS team · · 5 min read

The new case erector arrives on a Tuesday. Three crates, a commissioning engineer from the maker, and an envelope with the declaration of conformity in it. There's a CE mark on the plate. Everyone signs the handover on Friday and the maker's engineer flies home.

Week three, nights. The infeed guard interlock keeps dropping out. Your fitter has never seen this safety controller before. The manual is a PDF nobody has downloaded. The maker's service desk opens at 8am their time.

The mark on the plate says the maker did their job. It says nothing about whether you can keep the machine running safely.

UKCA or CE: which one?

For machinery sold in Great Britain, either mark is fine. GOV.UK's marking table lists machinery as "UKCA or CE" for the GB market. For Northern Ireland it's CE, or UKNI and CE (GOV.UK, product regulations by sector).

That's because legislation "came into force on 1 October 2024 to continue recognition of the CE marking"* for machinery. Businesses can choose which to use. The GB law is still the Supply of Machinery (Safety) Regulations 2008.

You'll still find older guidance with 2022 or 2024 end dates for CE. Those dates have been overtaken. If someone tells you a CE-marked machine can't be used in England, show them the GOV.UK table.

One more thing to watch. GOV.UK lists the EU's newer Machinery Regulation (EU) 2023/1230 against the machinery sector on the EU side. If you buy from Europe, ask the supplier which law their declaration is made under, and check with them that it's accepted for the GB market.

What the mark means

A UKCA or CE mark is the maker's claim. GOV.UK puts it as showing "that the manufacturer believes that their product meets the relevant product requirements" (GOV.UK, using the UKCA marking).

Believes. HSE's leaflet on buying new machinery goes further. It says the marking "in itself does not guarantee safety", and that you still need to check the machine is safe for use on your site (INDG271).

Behind the mark, the maker should have a technical file with test reports, design documents and risk assessments (GOV.UK). You don't get to see it. HSE's FAQ is clear that the file is confidential and the maker doesn't have to release it to customers. What they must give you is full instructions for safe use, plus things like noise and vibration levels (HSE, machinery FAQs).

What's still yours to check

PUWER makes you, the user, check the kit as well. Regulation 10 says work equipment must conform "at all times" with the design rules of the product law that applied when it was first supplied (L22, regulation 10).

The code of practice says you can check the mark and ask for a copy of the declaration of conformity (L22, paragraph 138). It then says to check you've had proper operating instructions, with information on leftover hazards like noise and vibration. You "should also check the equipment for obvious faults" (L22, paragraph 139).

So at handover, check:

  1. The plate. Does it match the paperwork? Maker, model, serial and the mark.
  2. The declaration. Does it name this machine, this serial and the right law? Is it signed?
  3. The instructions. In English, complete, and covering maintenance as well as running.
  4. The guards. Every one fitted, every interlock working, no gaps you can reach through.
  5. The e-stops. Press every one with the machine running. Our guide to testing emergency stops has a routine.
  6. The software. A backup of the PLC, HMI and safety program, and the passwords, before the maker leaves.

Lines, assemblies and your own builds

Join several machines into one line, with one control system and linked functions, and the line itself may need its own declaration, marking and technical file. That applies "even if each individual machine has its own CE or UKCA marking" (HSE, machinery FAQs). Whoever puts the line together takes that on. Sometimes that's an integrator. Sometimes it's you.

Partly completed machinery is different again. It comes with a declaration of incorporation, not a mark. HSE's FAQ says the part "must not be UKCA marked". It can't be put into service until the full machine it goes into has been declared in conformity.

And if you build a machine for your own use, you're the maker. HSE says you must mark it and meet the safety requirements of the regulations, "even if it is only for your own use". We cover where that line sits in machinery modifications.

The handover is where breakdowns start

Here's our view. Most new-machine problems have little to do with the mark. They come down to what your team knows when the maker's engineer leaves.

Week one, the machine is the maker's baby. Week three, it's yours, and the first breakdown usually lands on a night shift. If nobody on site was at the commissioning, nobody knows the safety controller, the fault codes or where the backup is.

That's the real cost. A two-hour fault turns into a two-day wait for the maker's engineer, with the line stood. We've written about when to call the maker's engineer or a local one. Have that answer ready before the machine arrives.

So put one of your own engineers on the commissioning, every day of it. If your team is too stretched to spare anyone, get cover for the line so they can be there. Have them walk the snag list, take the backups and write the first page of the PPM sheet with the maker in the room. Our guide to building a PPM schedule from the manual picks up from there.

What to do on Monday

  1. For your next machine on order, add the six handover checks to the purchase order. Make payment of the last stage depend on them.
  2. Pull the declarations for every machine bought in the last five years. Check each one names the right serial.
  3. Name the engineer who'll be at the next commissioning, and book cover for their shifts now.
  4. Check you have a safety program backup and passwords for every machine with a safety controller.

* GB and NI marking rules for machinery correct as of 6 November 2026. Check GOV.UK's product regulations by sector for the latest. Paragraph numbers refer to L22, fourth edition (2014, amended 2018).

Have an engineer at the handover

Running a site?

SiteSOS sends vetted maintenance engineers to your site for breakdowns and shift cover. You see the hourly rates first, and you approve the timesheet from your phone when the job's done.

Get engineers on call

Are you an engineer?

Breakdowns and shift cover near you, paid by the job. Offers show where, what, how far and the least you'll earn, and turning one down never counts against you.

Join as an engineer

Read next

More on legal duties on site