The shutdown pack lands in your inbox. Forty pages. Three firms on the conveyor rebuild, a crane in the yard, scaffolders on the mezzanine, and an electrical contractor swapping the main switchboard. On page two it says the work runs under CDM.
Then the contract spec for the job comes through. "SSSTS or SMSTS preferred." You've changed a hundred gearboxes. You've never set foot on a building site.
So do you need one? For breakdown cover and day-to-day maintenance, usually not. For the big jobs, where a factory starts to look like a construction site, it can be the ticket that puts you in charge of the crew. Decide which kind of work you want before you spend the money.
When does maintenance turn into construction?
More often than people think. CDM 2015 defines construction work widely. It includes the "repair, upkeep, redecoration or other maintenance" of a structure. It also covers the installation, maintenance, repair or removal of mechanical, electrical, compressed air, hydraulic and similar services "normally fixed within or to a structure". And a structure includes "fixed plant" (CDM 2015, regulation 2).
So a new main air ring, a switchboard swap, a mezzanine or a big fixed conveyor install can all sit inside it. A bearing change on a case packer on a normal night shift won't feel like construction to anyone. A two-week shutdown with five firms on site is a different job. Where your work falls is a question for the site's CDM paperwork. Ask before the day, rather than guess on it.
When more than one contractor will be working on a project, the client must appoint a principal designer and a principal contractor in writing (regulation 5). On a factory shutdown, the client is usually the factory. The project also has to be notified to HSE if it will last longer than 30 working days* with more than 20 workers* on site at once, or if it will exceed 500 person days* (regulation 6).
What the law asks for
The law doesn't name either course. CDM says a contractor appointed to a project must have the "skills, knowledge and experience" for the role (regulation 8). A contractor also can't put anyone to work on a construction site unless that person has, or is getting, the skills, knowledge, training and experience for the tasks they're given (regulation 15).
HSE's guidance comes closest to naming them. Where site workers are promoted to supervisor, they "should be provided with nationally recognised site supervisor training which includes leadership and communication skills" (L153, paragraph 171). On most sites, that's the slot SSSTS fills. SMSTS is the step up, for the person running the site.
The same guidance warns against reading too much into a card. "Sole reliance should not be placed on industry certification cards" as proof that someone has the right qualities (L153, paragraph 163). A shift manager who's hired a supervisor on a card alone, and watched the job drift, will know why.
Course length, content and refresher dates are set by the scheme, so check them with the scheme before you book.
Where it earns its keep
- Shutdown and install work, where you'd lead a small team alongside other contractors.
- Work for a principal contractor. They must plan, manage and monitor the construction phase (regulation 13), and they'll want supervisors who speak the same language.
- A move towards project engineer or shutdown coordinator roles.
- Sites that write it into the spec for anyone supervising contractors.
Here's our view. If shutdowns and installs fill a good part of your year, SSSTS is a sensible ticket to hold. SMSTS is for when you're the one running the job: the programme, the permits, the other firms, the daily briefing. If you'd rather be in the panel than in the site office, it's money you don't need to spend yet.
Where it won't help you
It's 2am and the sorter's down. Nobody on that floor asks for SSSTS. They ask who can read a drive fault and get the line back.
Both courses are built around running a construction site. They won't teach you to find a missing input, set up an encoder or chase a repeat trip. For breakdown work, look at the tickets that actually get you contract work, plus IPAF and PASMA if you work in tall warehouses.
If you manage the site
The same rules land on you from the other side. On a shutdown with several firms, you're likely the client, with duties of your own. Most of the pain on a shutdown comes from coordination. Five firms each think they've got the conveyor first. The scaffold's late. The electrical crew can't isolate because the mechanical crew holds the locks.
That costs real money. Every day the shutdown overruns is a day the line isn't making anything, on top of the contractor bills. So when a firm sends you a supervisor, ask what jobs they've run before. The card comes second. The guidance above backs you on that.
Our guide to planning a shutdown in 12 weeks covers the run-up. For what you owe each firm before they start, see contractors on site.
What to do on Monday
- Count last year's days on shutdown or install work with other firms on site. If it's more than a few weeks, look at SSSTS.
- On your next shutdown spec, ask whether the work runs under CDM and who the principal contractor is.
- Before you book SMSTS, be honest about whether you want to run jobs or fix kit.
- Keep your fault-finding skills and your electrical tickets in date first. They're what get you the call at 2am.
* CDM 2015 notification thresholds correct as of 7 November 2026. Check CDM 2015 on legislation.gov.uk for the latest. Paragraph numbers refer to L153, first edition (2015).