The palletiser gets a PPM every four weeks. Two hours, same sheet for the last eight years. Grease the nipples, check the chains, look at the belts, sign it off.
Last month it stopped for a day. The turntable drive gearbox failed. It isn't on the PPM sheet, because it wasn't on the sheet the installer left. The chains, on the other hand, have been checked over a hundred times and have never had a fault.
Reliability-centred maintenance is for exactly this. Your PPM is spending hours where nothing fails and none where things do.
What RCM is, without the binder
RCM has a reputation for workshops, consultants and spreadsheets nobody opens twice. Underneath, it's a handful of questions you ask about each machine:
- What does it need to do, and how well?
- How can it fail to do that?
- What causes each failure?
- What happens when it fails, and what does it cost?
- Can we see it coming, or stop it happening?
- If not, what do we do instead?
Your fitters already know most of the answers. They're in their heads, and in the job sheets. RCM just makes you write them down and act on them, one machine at a time.
Start with one machine
Don't try to do the site. Pick the machine that hurts most when it stops. If you're not sure which that is, rank them first with criticality ranking.
Then get three people in a room for an afternoon. The fitter who knows it best, an operator from the shift that runs it most, and someone with controls knowledge. That last one matters. If nobody in the room understands the drives and the PLC, every failure you list will be mechanical. Those just happen to be the failures your team knows how to see.
If you don't have that person on staff, it's worth paying for a day of one. It's cheaper than finding out what you missed at 2am. Our piece on fitters, electricians and controls engineers goes into who covers what.
List how it fails, not what it is
Walk the machine section by section. For each part, ask how it stops doing its job. Then ask what causes that.
"Gearbox" is not a failure mode. "Output bearing wears through lack of oil" is. So is "seal leaks, oil level drops unnoticed". Each one points at a different task.
Use your breakdown log and the CMMS to check yourselves. What has actually failed in the last two years? If it's not on your list, your list is wrong.
Ask what each failure costs
Now sort the failures by what happens when they occur. We use four buckets:
- Someone could get hurt.
- The line stops, and you know about it straight away.
- Quality or output drops, but the line keeps running.
- It fails and nobody notices.
That fourth bucket is the one to worry about. HSE's code of practice for PUWER makes the point. A fault that affects production "is normally apparent within a short time". A fault in a safety-critical system "could remain undetected" unless safety checks are built into the maintenance (L22, paragraph 71). A failed interlock, a stuck relief valve, a standby pump that won't start. These don't stop the line. They wait.
Pick a task for each one
For each failure, choose the cheapest thing that works.
If you can see it coming, watch for it. Vibration, temperature, oil condition, a noise the operator can hear. That's condition monitoring, and it often costs less than people think.
If it wears out on a known pattern, replace it on a schedule. Belts, filters, some seals.
If it's hidden, test it. Function-test the interlock. Stroke the valve. Start the standby pump. Write down the interval and who does it.
If none of that is worth it, let it run to failure on purpose. Hold the spare, write the fix down, and know who you'll call.
That last option needs care. Run-to-failure is only cheap if the repair is quick. If the spare is on a 12-week lead time, or the only person who can fix it is on holiday, it isn't cheap at all. Check your critical spares and your callout list before you sign it off.
Where the law draws the line
You have more freedom here than you might think, with one exception.
The PUWER code says maintenance should be "targeted at the parts of work equipment where failure or deterioration could lead to health and safety risks" (L22, paragraph 73). Where safety-critical parts could fail and lead to "immediate or hidden potential risks", it says you need "a formal system of planned preventative or condition-based maintenance" (L22, paragraph 75).
So run-to-failure is fine for a conveyor roller. It's not an option for a guard interlock. Keep those two lists apart.
The code also says to follow the manufacturer's recommendations (L22, paragraph 74). Our view is that RCM sits on top of the manual, not in place of it. Start from the manual, then add what your failure history tells you. Our guide to building a PPM schedule from the manufacturer's manual covers that first step.
Put it back in the PPM
The output of all this is a new PPM sheet for one machine. Tasks you added, tasks you dropped, and the reason for each. Keep the reasons. In two years someone will ask why the chain check went from four weeks to twelve.
Then review it. L22 says extra maintenance may be needed where arduous conditions are foreseen or have been experienced in use. It adds that these measures may need reviewing in the light of operating experience (L22, paragraph 76). Speed changes, new products and a third shift all count. Put a date in the diary for twelve months on.
Once the first machine is done, the second takes half the time. By the fifth, your team will be doing it without the meeting.
What to do on Monday
- Pick the one machine that hurts most when it stops.
- Book an afternoon with a fitter, an operator and someone with controls knowledge.
- Pull two years of breakdowns on that machine and bring them to the session.
- List every hidden failure on it, and check each one has a function test.
Paragraph numbers refer to L22, fourth edition (2014, amended 2018).